The project’s expected completion time is 15 weeks
There is a 71.57% chance the equipment will be in place by the 16 week deadline
Five activities (A, C, E, G, and H) are on the critical path
Three activities (B, D, F) have slack time and are not on the critical path
A detailed schedule is available