28.2 Inspection of the supplies shall be done by the SRT Inspecting Engineer(s) at the place of manufacturer for all stages of production to determine conformity with the referenced and relevant specifications and drawings. The supplies shall be to the satisfaction of the Inspecting Engineer (ร) whose decision shall be final and bound on the awarded bidder in all cases. Should any of the parts and materials be found defective or fail to comply with the tests, analysis or other requirement of the specification, they shall be rejected. The decision of the Inspecting Engineer (ร) shall be final and binding on the awarded bidder in all cases. Nevertheless these inspections do not in any way relieve the awarded bidder of the warranty and his responsibility to deliver in the stipulated time such work or material as is in accordance with the drawing and the relevant specification.