Notice of Delay Penalty:
As you have not yet completed all payment within January 15th, 2015, subject to General
Conditions, Liquidated Damages shall apply and delay
penalty will be at the rate of 10,000 THB per day of the Contract
Price from the date following the specified date of completion up
to the actual date of delivery of activities correctly and completely.