Q47. Which of the following is an appropriate activity that is performed in “project scope
management” defined in the PMBOK (Project Management Body of Knowledge)
Guide?
a) Organizing a project team and developing staff members
b) Defining all activities required for a project without any omissions
c) Identifying the stakeholders of a project and deciding the communication method
d) Identifying the project risks and considering appropriate action plans