Dear K Leif/K Apichai
regarding to we have daily meeting for update work progress B1 inspection GT-21 ABPR2 and K Leif informed that new fact finding part including inner ring GV1 will be delivery to site ABPR2 on Friday evening ,Oct 14,2016 and assembly part to turbine module already finish and New Combustion chamber &all 30 burner have been completed to installed only waiting fact finding part
if we are compare progress with master plan schedule look like delay/or behind schedule around 1-2 days,therefore after new fact finding part delivery to site could you team please speed up working full time 2 shift(24 hrs working ) to meet original target plan schedule for start up unit on Oct 19,2016
and both party will be close monitoring update day-by-day