We regret to inform that after careful consideration, we determined that your proposal was not the most advantageous to TTCL at this time. Our decision is based on technical because steam production (without supplementary burner) that we need is higher than your proposal and SCR cannot be installed after GT before HRSG because the catalyst is not suitable for high temperature as per current condition.
But we look forward to having the opportunity to work with you on suitable future projects.
Thank you again for best effort to response our request.