The Outline and Main Facilities of RDF Manufacturing Demonstration Plant
The combustible materials of household waste (200ton/day) carried into Sudokwon landfill
site are made into RDF by crushing and sorting in RDF manufacturing demonstration plant
invested total 23milion dollars approximately. The construction of this plant was started in
November 2009 and completed in April 2010 include 8months test operation (July 2009 ~
March 2010). This plant is located on ‘Waste-to-Energy Town’ in Sudokwon landfill site of
Incheon city and the area is 9,600m2
. This plant is composed of 200ton/day pretreatment
facility and 100ton/day RDF manufacturing facility. Major facilities are intake-feed facility,
mechanical pretreatment facility, dryer, pelletizer and dry exhaust gas treatment facility