TUK (Steller Systems) provided their draft proposal for the siting of the Decompression Chamber on the after deck of the
ships (Slide 19). It was considered necessary that the Decompression Chamber supplier confirmed that the siting of the
chamber did not have any detrimental impact on its operational function. RTN agreed to hold discussion with Cowan
Manufacturing PTY Ltd to confirm that the proposed installation site was satisfactory.
ACTION: RTN to hold a meeting with Cowan Manufacturing PTY Ltd to confirm that the proposed installation site of the
Decompression Chamber was suitable for operational use and to inform TUK of the outcome by 31 Aug 16.