Contractor shall ensure that under no circumstance is power to be applied to
sensors until final installation inspection is completed.
Contractor shall coordinate with GBS Operator team prior to commencement of
any loop checking.
Perform Loop check by below following steps;
a) Close Fuse terminals to power up sensor and ensure correct connection by
checking laptop display.
b) Ensure that the laptop configured range can display the sensor’s measurement
range.
c) Check the real time measurement of sensor at the laptop.
Refer Instrument Index no. TH-GBS-4A-WP1-INS-LIS-0001 and TH-GBS-4AWP2-
INS-LIS-0001 and the Soft Signal Index to be provided by Company.