Section 5.01 Time Interval between Invitation and Submission of Bids
(1) The time allowed for preparation and submission of bids shall be determined with
due consideration of the particular circumstances of the project and the size and
complexity of the contract. Generally, not less than 45 days shall be allowed for
international bidding.
(2) Where large civil works or complex items of equipment are involved, generally not
less than 90 days shall be allowed to enable prospective bidders to conduct
investigations at the site before submitting their bids.