Mechanical Room #1
• Completion of backfill of HDPE filtration pipe under ramp at center island to be completed
• Excess dirt, debris and broken concrete to be removed from filtration room.
• Pump Pit
o Safety railing to be installed around perimeter
o Stairs or ladder to be installed to permit access to the pump pit
• Concrete in the chemical room does not slope to drain
o Chemical tanks to be put on concrete housekeeping pad similar to what was done in the other mechanical rooms.
• Complete concrete works at entrance door at bottom of the stairs
• Installation & alignment of mechanical room access door to be completed
• Grating for submersible pump pit to be installed
• Plant room and filter room to be cleaned prior to handover to the client
• Equipment should be cleaned prior to handover to the client
• Mechanical room entrance door to close and lock