Having the proper resources in place and ready to complete their assignments will facilitate a smooth transition to the new system. The detailed cut-over schedule was published last week which contains all of the conversion activities. Below are some of the key activities the businesses will complete during the conversion weekend:
1. Clean up all COGI and KPAC errors. (before inventory extracts)
2. Plants not using Demand Planning will manually load their VSF forecasts to PRD. MD61
3. The open Indirect P.O.s will be extracted and sent to the businesses for manual entry into PRD. Business will use mapping tables to enter the orders. The old P.O. number goes into the tracking number field and then the open P.O. report can be created that maps the old P.O. and new P.O.
4. The direct P.O.s will be loaded by program. A list of the loading errors will be sent to the businesses for corrections and manual reentry.
5. All businesses will need to cancel any open deliveries and shipments. Must be done before the sales order extract.
6. The open Sales Orders that will be manually reentered will be extracted and sent to the businesses. (primarily plant level intercompany sales orders and KTH).
7. For sales orders, inquiries and quotations that will be loaded by program (INV, KAPL, INDI, NANC), a list of the loading errors will be sent to the business for corrections and manual reentry.
8. A list of 3rd party P.O.s, will be sent to the businesses to cancel these orders.
9. A list of open inspection lots will be sent to the businesses using QM for processing Usage Decision (to either UU or blocked). Must happen before the inventory extract. The list will then be sent to AP with payment block instructions.
10. Businesses that are doing interplant (INDI) and intercompany will need to clear the in-transit accounts. A list of in-transit inventory based on the GI being done in the sending plant but not yet received, will be sent to the receiving plant. The GR will be done in the legacy system before the inventory extract. These P.O.s will be excluded from the P.O. load file.
11. The IM and WM inventories will be loaded by program. A list of loading errors will be sent to the businesses for corrections and then manual entry.
12. Extract Letters Of Credit and send to business for manual entry.
13. A file will be provided to the businesses to manually load sub-contract inventory, and new vendor code mapping will be applied.
14. A file of consignment inventory will be extracted, vendor mapping applied, and the list sent to the business for manual entry.
15. Subcontract inventory (material provided to vendor) will be extracted separately, vendor mapping applied and the list sent to the businesses for manual entry.
** Note: Finance departments have already released standard costs in PRD
There will be key activities the business will need to complete during the conversion weekend
Business Conversion Activities - Steps to Success
Having the proper resources in place and ready to complete their assignments will facilitate a smooth transition to the new system. The detailed cut-over schedule was published last week which contains all of the conversion activities. Below are some of the key activities the businesses will complete during the conversion weekend:
1. Clean up all COGI and KPAC errors. (before inventory extracts)
2. Plants not using Demand Planning will manually load their VSF forecasts to PRD. MD61
3. The open Indirect P.O.s will be extracted and sent to the businesses for manual entry into PRD. Business will use mapping tables to enter the orders. The old P.O. number goes into the tracking number field and then the open P.O. report can be created that maps the old P.O. and new P.O.
4. The direct P.O.s will be loaded by program. A list of the loading errors will be sent to the businesses for corrections and manual reentry.
5. All businesses will need to cancel any open deliveries and shipments. Must be done before the sales order extract.
6. The open Sales Orders that will be manually reentered will be extracted and sent to the businesses. (primarily plant level intercompany sales orders and KTH).
7. For sales orders, inquiries and quotations that will be loaded by program (INV, KAPL, INDI, NANC), a list of the loading errors will be sent to the business for corrections and manual reentry.
8. A list of 3rd party P.O.s, will be sent to the businesses to cancel these orders.
9. A list of open inspection lots will be sent to the businesses using QM for processing Usage Decision (to either UU or blocked). Must happen before the inventory extract. The list will then be sent to AP with payment block instructions.
10. Businesses that are doing interplant (INDI) and intercompany will need to clear the in-transit accounts. A list of in-transit inventory based on the GI being done in the sending plant but not yet received, will be sent to the receiving plant. The GR will be done in the legacy system before the inventory extract. These P.O.s will be excluded from the P.O. load file.
11. The IM and WM inventories will be loaded by program. A list of loading errors will be sent to the businesses for corrections and then manual entry.
12. Extract Letters Of Credit and send to business for manual entry.
13. A file will be provided to the businesses to manually load sub-contract inventory, and new vendor code mapping will be applied.
14. A file of consignment inventory will be extracted, vendor mapping applied, and the list sent to the business for manual entry.
15. Subcontract inventory (material provided to vendor) will be extracted separately, vendor mapping applied and the list sent to the businesses for manual entry.
** Note: Finance departments have already released standard costs in PRD
There will be key activities the business will need to complete during the conversion weekend
Business Conversion Activities - Steps to Success