I believe some of them were surveyed, please confirm which one that we surveyed then let Willich to fabricate as their record krub. Also priority for skids that we have to do during total SD first (hot or cold surface) and which one can be done online krub.
Is it possible to let Willich survey the rest by first day onboard during SD and send details to fabricate from shore then send to field by 5-7 days to continue after first lot krub?