HIS team has joined the team meetings. In the meeting Were informed about the time needed to collect. specification is to be completed by the end of April.
By the conclusion of the meeting together is the first job of Golive October 1, 2015 is required to perform the Interface Data between HIS Middleware SAP.
With regard to Interface 3, as follows.
1. Interface Revenue + Onward + Not print.
a. Status now is to create spec and send the information to wait for the project Middleware confirm spec.
2. Interface Payor office (Master Data).
a. Status Now is not the Spec Middleware will send the information to the project pending HIS appointment to talk with SAP middleware, now I do not have a date.
3. Deposit management system
a. Staus now the project is meeting the Super User Access to Information 29/04/2015 to determine the specification. I thoroughly