4.3 Material Handling Equipment
Material handling equipment of the raw material was not good
enough that is to say trolley was used to move in one direction
and pathway was not flexible enough due to untidy
arrangement of the things.
4.4 Storage of Finish Good Material
Storage area for finish good material was 156 square feet. the
plant at the present time could contain only finish good
material .after improvement it had more space to install new
assembly line.
4.5 Analysis Factory Layout on SLP
According to study of manufacturing process, it was found
that long distance could be reduced for moving material from
assembly line and the problem about unless area could be
solved .the way to improve plant to apply SLP method to
make the flow continually by arranging the important
sequence of the manufacturing. Then the relationship of each
activity in closeness area was considered to make the
relationship of activity.
4.6 Proposed Layout
The important sequence of each activity was rearranged from
the most important one to least important one. Based on
modifying plant layout were deployed .the original plant
layouts represent a while modified plant layout represent B.