As EG is Hardscape façade sub-contractor for Central Embassy Project. We are also responsibility for installation stone skirts at main entrance gate and the façade around building at Gucci and Hermes area. We are need to install stainless skirt (according to attach fine) so it have some part adjoin with PISA’s entrance work.
Therefore, we are pleased request to PISA to demolish entrance gate above on 16th October 2014 at 10:00 PM for EG stainless skirt installation to match with drawing that designer’s design and Central Embassy project already approved shop drawing. If PISA has question, pleased kindly contact to our project manager. (Khun. Jirapat 096-6685575)