1.1 Project Status Update
At the end of January 2016 period, the Preakasamai Waste to Energy Project is progressing in line with an early schedule.
The accumulative of Overall of progress, including all Engineering, Procurement and Construction activities, increased to 23% to date versus the target plan of 19%.
Engineering achieved 75% progress. Process design product was confirmation with major package equipment. Subsequent engineering activities are ongoing. Process Design products, Storage Tank Design, or Piping Design are being developed. Technical Specification of Fire Water Pumps was generated while other BOP equipment specifications are under preparation. Electrical Design is proceeding through several discussions with major Packages. Cooling Water Tower and Water Treatment Plant were finalized evaluation. Distributed Control System is ongoing cooperation with potential Thailand vendors for evaluation.
Procurement progress is accumulative to 18% to date versus the target plan 15%.
Site preparation activity is ongoing, the accumulative of Construction progress is 5% to date versus the target plan 4%.
APCON progressively are proceeding so as to finished mostly of piles drive in the following
next month.