MY17 C140 Hood Insulator follow the plan or not – Pending 2D Drawing then CF pending , Need K.Somchai asking for document from Roberto and CC me.
MY15 GMI700 Cowl Top and Outer dash PPAP and EDI –follow up New EWO add hole and relocate hole is done and Review part with CF have 4 comment
Outer dash
1.Check gap between section gage and CF surface is in spec or not(Need to check part thickness in CAD also).
2.Check shape of part between left and right (Difference) is follow CAD data or not.
3.Add point check on section gage from 1 point to 3 point
Cowl top
4.Improve trim line of part
MY15 GMI700 Carpet jetblack PPAP and EDI -- Waiting PR manual order from Thitipong within Friday 23 May 2014
PCPA audit – Please self-audit and send to me by 19 May 2014 – Audit 27 May 2014