1. The team members had spent 493.4 hours so far compared to a plan of 467 hours, so they had spent 5% more hours on the job than planned.
2. The team had accomplished 22.3 EV of work to date, compared to a planned 28.2 PV. This was a 26% slip in the schedule.
3. For the tasks the team had completed, the members had spent 458 hours compared to a planned 354.3 hours, or a 23% underestimate.
4. At the rate of 22.3 EV in 7 weeks, the team was earning 3.186 EV per week.
5. At this rate, the team would reach 100 EV in(100 - 22.3) / 3.186 = 24.39 weeks.
6. Therefore, at the average EV rate the team had earned so far, it would take 24.39 + 7 = 31.39 weeks to complete the 17-week project, putting them 14.39 weeks behind schedule.
1. The team members had spent 493.4 hours so far compared to a plan of 467 hours, so they had spent 5% more hours on the job than planned.2. The team had accomplished 22.3 EV of work to date, compared to a planned 28.2 PV. This was a 26% slip in the schedule. 3. For the tasks the team had completed, the members had spent 458 hours compared to a planned 354.3 hours, or a 23% underestimate. 4. At the rate of 22.3 EV in 7 weeks, the team was earning 3.186 EV per week. 5. At this rate, the team would reach 100 EV in(100 - 22.3) / 3.186 = 24.39 weeks.6. Therefore, at the average EV rate the team had earned so far, it would take 24.39 + 7 = 31.39 weeks to complete the 17-week project, putting them 14.39 weeks behind schedule.