The schedule assessment is usually reported using a schedule plot (e.g., a bar chart) showing the
planned (i.e., target) and actual schedule activity status. The assessment can also be displayed in a table
showing a percentage or factor that expresses the extent that the schedule is ahead or behind at given points
in time. To help assess management priorities, additional schedule status reports may include lists of
activities sorted by pending planned start dates (activities requiring immediate attention), pending planned
finish dates, or by total float (activities with most immediate potential impact to project completion)