Dear Kong,
I have comment for Item 9, pointer 4 ‘Suggest best time for commissioning before June 2018’. During the meeting, Building Team was requested to study with SMCC and TKS if the commissioning of the paint shop equipment can start from 1 June 2018 (if instruction to proceed with construction is given on 1 Jan 2016). As the commencement date is undetermined, can we amend the minutes as below for pointer 4: -
‘FHI requested for the commissioning paintshop/bumper paint equipment to commence from the start of month 18th onwards’
Thank you.