Due to if we goes to the way of revise the EIA report. The 3rd party who provide the revision EIA will request the change order cost as well. We assume that it will be expensive cost to revise the EIA and normally when we request to change they will have addition concern and need Regarding to the clause in contract below (Clarifications), please kindly confirm that EIA is required more that TOR or not?
In addition, in case that we luckily on the TOR statement that not mentioned about the number of Jockey pump, please kindly ensure that our TOR has not mentioned some kind of the work shall be proceed according to the international standard (this is because we breaks the rule of NFPA20), do we have any concern of this matter or not, if we decided to enforce TTCL to provide such Jockey pump with free of charge.