Check cases and results of pre-examines that have conducted for the past 1 year. When having field inspection, check whether there were the below occasions; if there were, have field inspections and interviews to check whether pre-examination has been conducted for the concerned case.
(1) Installation of / changes in facilities or utilities.
(2) Changes in layout inside of buildings (including walls. except for partitions) or changes in the purpose.
(3) Installation or application of dangerous devices, fire fighting facilities, gas-using equipments, storage of hazardous materials.
(4) Introduction of inflammable and combustible materials and harmful chemicals or changes in their handling methods and using/storing amount.
(5) Changes in factors of environmental pollution.
(6) Changes in Interlock System.
(7) Changes in operating condition or process.
(8) Other changes that a site's EESH department leader thinks a review is necessary. (only when it is changed to the same kind.)
(9) Purchase or design of energy facility, equipments, or system including buildings.