Dear Khun Samran
The welding work of the 1” and ¾ “ steam lines is mostly finished.
So, the work can start immediately.
For the 6” steam line 160 m. will be done after first firing of Boiler plant
which will be soon.
As per site situation, quantity of pipe , fitting etc. may be deviated from the number
given to you by several reason. To close the PO and allow you to start the work immediately,
you are requested to checked quantity at site by fixed the unit rate as proposed in price breakdown
revision 02.
The work volume shall be approved by ZCN before commencing.
Khun Wongwalai , please proceeding the PO as per price breakdown and condition revision 02.
The actual measurement will be investigated and agreed by both parties.