Dear All,
Attached is the Design Memo raised by AFW regarding to Operator Training Simulator (OTS) required for the CFP project. According to the section 4.1.1.14 of the FEED ITB, TOP will provide information of which the new process units are required for OTS implementation. This information is critical for AFW to ensure the cost of OTS to be included in the +/- 10 % cost estimate. Required hardware and software for OTS must also be included in the scope of the DCS contractor later.
In order to reply to AFW, I would like to have your feedback of which new process units are required for OTS implementation for the CFP project. Since some new units are similar to existing units such as CDU, HDS, PSA etc. I am not sure if they are really required for simulation or operator training or not.
Your feedback before 20 November is highly appreciated.