If, subject to the Late Normal Operation Period Rules, during Commissioning the Supplier is prevented, for more than 14 days, from carrying out the Tests on Completion by a cause for which the Owner is responsible, the Supplier shall carry out the Tests on Completion as soon as practicable thereafter.