1. Note the meter lengths indicated was copied from the yard and we clarify that we are working on full container loads on the scheduled stated. You can therefore load to full load for the following schedule.
2. This schedule issued in Nov 2015 covers delivery upto April 2016 only. It does not cover the whole PO. The schedule shall be reviewed in January and an extended schedule on the remaining quantities will be issued. (Note the yard has import quota constraints that is dependent on the Chinese Custom and the progress as there is a time limit between import and re-export out to HK.) There is largely a three months advance notice per this schedule.
3. In terms of the final quantities for the project, this is yet to finalize and adjust. The existing PO is based on quantities at the start of the project, re-adjusted one time at best but keeping the PO amount to avoid redoing down payment issues. The absolute final quantities of the project is yet to finalize with various drawing modifications and wastage.
Hope the above clarifies your queries and thanks to confirm on arrangement for January 2016 as stated.