Regarding you inform us that your subcontractor (SAS Tech) will plan to Installation plan LAB Metering skid in Chemical loading area.
Please raise them provide completely all information before send us plan 1 week because it’s a brown field. (your propose on 6 July 2015 may not possible because it too short notice)
We have to consult Operation team to find time slot to do this activity by not interrupt operation selling in that area as much as possible.
However, you shall prepare all document and send us review before start work 1 week,
- Safety work permit and clearance certificated
- Transport and lifting Procedure
- How many hour for your plan to finish this job ?
- Do you required close a Chemical loading area ? or close a road shall speicify ?
I observed that your site is not ready to installation civil work is not finish as picture attched. (road is not fully pave and many waste inside area is not cleaning)
In the same time, I will cooperate with Operation team for raise them know and ask them for possible schedule.
I will infom you schdule from operation later.