Dear P’Phanupol
Sorry for my mistake,
Currently I count the progress based on the actual work it mean that for steam main pipe line and Kulthorn metering only and I plan to increase the progress to 100% when the main pipe line and KK metering are install and test complete, that is because the previous progress I forgot separate the percentage of Unilever work and Cadbury work for each portion.
However, I will note the reason on overall progress report that “The Progress are based on the actual work without the Unilever metering and Cadbury metering”
Could you please to consider krub.