No Problem Brendan, understand we are working to CUEL request,s ( example continue working to dismantle all scaffolds so they can WASH down on night shift after the level released, ) then release next level scaffold for inspection then dismantle, Brendan don't think for sure its about cost per workers as we are per day work and agreed with them, main concern as its a cost to CUEL of 200,000 US dollars per day regarding each day delay per day of sail away,
Believe me feel we are going to make this date as you know last man frees all, unfortunately scaffolders are last man frees all , I will show photos of our Supervisors on the 25th if the sail away is successful, they will be wearing Santa Claus hats sorry Guys but for sure lots of pressure to meet Schedule's
A MERRY Christmas To All.
P.S yes Brendan for sure Fatigue comes into play decided after discussion to send Khun Gong home today he looked shattered he was working until 9 pm last night good money for them and good money for us , noticed ( TANWA ) looks the same poor guy getting there,
one more day tomorrow for major dismantles and we are there,
Again all have a merry XMAS to all.