We would like to inform that most drawings were not approved for fuel and ash systems submitted by bulk.
1) Fuel system: Issues
a) GA for double screw is not yet approved. Size of Bulk screw was not fitting into already constructed pit at site. So we expected some rework at site. Hence we suggested bulk to carry out design changes in screw suiting our pit size at site.
Till date bulk has not submitted revised drawings.
2) Ash system: Issues
Most of bulk GA drawings were not approved and was supposed to submit all revised drawings.
After crosschecking with our team they informed me that the 3D model already was done by ourselves and submitted to you already. Is it possible to use it? (For the 3D model i use for ref. only, because the 3D model will be reconstructed cannot transfer 3D model from auto cad file to Teka )
Following that we basically only required the 2D drawings and therefore we would like to ask to reduce the estimated hours from 50 towards 30. Is that possible? (I will reduce the man hour from 50 hr. to 40 hr.)