Anpon just informed us their PD and Manu only valid to Dec 2014, it will take 3-4 months to get the ICAMA certificate or manu license , if we apply now ICAMA certificate , we may get the certificate Oct-Nov 2014., can DOA deal with the ICAMA certificate (Nov 2014 get ICAMA certificate, , PD or manu license valid to end 2014) on time (before Dec 2014)?
But our factory can apply to delay (or let's say renew) PD or manu license, the number of PD and munu license is the same.
Please check with DOA, what should we do? Apply now or wating after Dec 2014 when our factory get the new PD or manu (valid time from Dec 2014--Dec 2017--2018).