Dear Kha,
Based in what we have agreed with FMC, we should Power test any single process equipment till we have the walk down and the MC completed ! Wither its functional or any other type of test.
Dear Duane,
Can you please finalize the testing procedure and make sure its clear to every body, as we can not agree something with FMC and do something els on site !