Stage 3 (5 years 2014 - 2018)
· 2014: Commissioning of 180 MW Kamchay hydropower plant,
· 2015: Commissioning of 125 MW Russey Chrum hydropower plant,
· 2016: Commissioning of 110 MW Stung Atay Hydropower plant,
· 2018: Commissioning of 465 MW Sambor hydropower plant
· 2020: Commissioning of 207 MW Lower Se San 2 and 222 MW Lower Srepok 2
hydropower plants
· After 2020: Commissioning of 980 MW Stung Treng hydropower plant
· After 2020: Commissioning of Stung Chay Areng 260 MW hydropower plant.