5.1 Preparing Work
a) Materials and equipment shall be followed the specification specified in working
drawing.
b) Checking the condition of equipment to see that it is not loose or damage and is in
perfect condition to utilized.
c) Cleaning out the dirty material to ensure that it is free from the dirt.
d) The surfaces of materials shall be thoroughly cleaned before the welding.
5.2 Setting The Deformed Bar
• Installing the deformed bar in column and pile (Holding the bar in place).
The deformed bar shall be installed between the reinforcement bar and the other
reinforcement bar by using binding wire to connect bar together to avoid welding method.
(Please see Fig. 1)