Just short minutes that I take form Artinian site Meeting 24.06.2014
In the meeting
1. The LV8 Project Schedule; JHT show the timeline for furniture work finish is 4th July 2014 and other is 10th July 2014 without the items that K.Saro not submit yet. (ie: engineer flooring, wall stone… ) and JHT do cement leveling first for the K.Saro area to received only engineer wood level.
2. Glass Lift up issue: K.Ton said that he had talk with glass peoples on last Saturday to find the other way for carries the Glass panel by over the Lift roof with MITSU to helping to drive.
My noted: I have response that I have not heard this before. So I have appoint the glass people with us to talk with JRM on 1pm today.
3. Artinian ask JHT to quote for the LV8 two Window glass and frame in the standard color and send them quotation.
Action: we already give K.Suwit to quote on this.
4. Air service panel already change size in their M&E requested.
5. Still follow their regulation: use level 1 toilet and no smoking in site work.
In the LV8 site with K.Arto & K.Saro
1. K.Arto comment for our ceiling finishing and quality.
Action: Inform K.Suwit to rectify
2. K.Saro comment for Lighting design,
JRM will submit with K.Saro and have meeting for design change.
3. K.Saro/ K.Arto comment that Counter Reception top was to small need to enlarge from 600mm to 750mm.
Action: Ar Cheng will quote on this addition as K.Saro signed on the drawing that show the present dimension.
4. K.Saro want to add acrylic panel in decoration for selection room wall (two side) to protect the wall crash.