3. Pre-Commissioning Pre-Commissioning activities start when the plant การแปล - 3. Pre-Commissioning Pre-Commissioning activities start when the plant ไทย วิธีการพูด

3. Pre-Commissioning Pre-Commission

3. Pre-Commissioning
Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this reason the plant should be separated into easily manageable system package, each system package will be Pre-Commissioned as a whole and isolations at the boundaries of the system package will be maintained until the completion of Pre-Commissioning activities. Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument installations, running-in of equipment, flushing and cleaning activities, drying etc.
3.1 Mechanical Completion Check & Interim Handover
Immediately prior to the hydro test of each system, a Punch-List will be performed by an integrated Punch- List team consisting of construction, and EPC Commissioning
Engineers (from relevant disciplines). When all “A” type items have been cleared and a small but manageable amount of “B” type items are left, a handover can be progressed from the construction to the commissioning group. Since mechanical completion has been achieved with agreed exception items, it is classed as an interim handover to permit construction completion and Pre-Commissioning activities simultaneously. Control and responsibility of work on the system rest with the commissioning group. Any construction work will require written permission from the Lead-commissioning Engineer of the particular Process Unit. Permission will be granted on a job by job basis. This would involve a line-by-line detailed check of the actual physical installation against the latest P&I diagrams issue, job specifications, piping hanger and support drawings, vendor drawing, etc., for erection of the unit in accordance with all drawings and applicable specification. The systems would also be checked from an operating viewpoint for proper location and orientation of valves, vents, drains, steam tracing and traps, sample connections, etc. Punch lists of deviations,
Installation errors, missing items, etc., shall be prepared and given to the appropriate construction department for correction or completion. Also included in this inspection and check-out would be:
• Vessel Internals - This would include going through each tower and vessel to check the installation of trays, baffles, demisters, spargers, etc., and verifying that the dimensions of all weirs, downcomers, distributors, thermowells, etc., are within specification and are properly oriented, as well assuring the internal cleanliness of each vessel prior to final closure.
• Non-operating Adjustments - All non-operating adjustments, packing of pumps and valves and cold alignment of equipment performed by the construction subcontractors should be spot checked, witnessed or periodically inspected to ensure proper records are being kept and recorded for turnover.
• Piping - Check lists would be prepared on each hydrostatic test system before the system is released for hydrostatic testing. Completion of this punch lists by the construction contractor would be required before the test system is released for testing. Post-hydro punch lists would be prepared and followed through on to ensure that the systems were fully completed and ready for pre-commissioning.
• Electrical Installation - Each electrical circuit and motor installation and their electrical polarity check and insulation resistance measurement would be demonstrated by electrical subcontractor to the Commissioning Subcontractor Team.
• Instrument Installation - Review of instrument installation of correctness according to the instrument drawings and specification. The Commissioning Subcontractor Team would witness and/or approve all instrument calibration and check out procedures or work performed by instrument subcontractor.
• System Pressure Testing - Although the construction contractor is responsible for the actual pressure testing of each system prior to mechanical completion, the Commissioning Subcontractor Team would review the test program and the methods used to ensure satisfactory tightens.
3.2 Pre-Commissioning Period
The site phase of the project will commence at approximately 60% construction completion and activities will be mainly centred on:
• Progression of all of the procedures developed during the Home office phase of the project
• Co-ordinating system turnover and completion
• Monitoring and reporting progress
• Co-ordinating resources, including sub-contract and vendor support
• Liaising with licensors
Main activities developed during Pre-Commissioning phase are:
Punch-Listing
Punch-Listing will be undertaken on a systems basis. An integrated team will be formed to participate in Punch-Listing. An initial Punch-List will be undertaken immediately prior to system handover for Pre-Commissioning purpose. This will probably occur at around the hydro test time. Punch-List items generated at this stage will be incorporated into the Project master Punch-List system. A final Punch-List will be undertaken by system immediately prior to the commencement of commissioning activities. This will be a less stringent
Punch-List and aimed at checking the system over before introducing hydrocarbons
Utilisation of the Pre-Commissioning check sheets will assist in completing a full range of required checks. Punch-Listing progress will be recorded on an A3 set of P&IDs.
System Cleaning
This would include directing the cleaning of systems either by flushing, blowing or chemical cleaning by issuing directives for the necessary temporary connections, utilities and proper line up of the system to be cleaned. When the services of a chemical cleaning subcontractor are required, the Commissioning Team will monitor his performance to ensure a satisfactory cleaning job. Before each system is closed for operating, the lines and equipment would be inspected for cleanliness. Cleaning progress will be recorded on an A3 set of P&IDs.
Equipment Run-In
This would include planning and co-ordinating Vendor representatives for the running in of the equipment and obtaining the necessary utilities to accomplish the run-in for equipment such as blowers, pumps, compressor, motors, turbines, and other machinery or mechanical equipment without process fluids before start-up.
Vessel Loading
This phase would ensure that all catalysts, packing, resins and desiccant loading is performed in a proper manner and accurate records and samples of each material loaded are retained. When all the activities foreseen in the Pre-Commissioning phase (the Process
Units will be ready to receive hydrocarbons, most of the utility systems will be live to the respective units and all of the hydrocarbon lines will be positively isolated at the unit battery limits) have been performed successfully a Ready for Commissioning Certificate will be issued and so Commissioning activities can start.
0/5000
จาก: -
เป็น: -
ผลลัพธ์ (ไทย) 1: [สำเนา]
คัดลอก!
3. Pre-Commissioning Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this reason the plant should be separated into easily manageable system package, each system package will be Pre-Commissioned as a whole and isolations at the boundaries of the system package will be maintained until the completion of Pre-Commissioning activities. Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument installations, running-in of equipment, flushing and cleaning activities, drying etc.3.1 Mechanical Completion Check & Interim HandoverImmediately prior to the hydro test of each system, a Punch-List will be performed by an integrated Punch- List team consisting of construction, and EPC CommissioningEngineers (from relevant disciplines). When all “A” type items have been cleared and a small but manageable amount of “B” type items are left, a handover can be progressed from the construction to the commissioning group. Since mechanical completion has been achieved with agreed exception items, it is classed as an interim handover to permit construction completion and Pre-Commissioning activities simultaneously. Control and responsibility of work on the system rest with the commissioning group. Any construction work will require written permission from the Lead-commissioning Engineer of the particular Process Unit. Permission will be granted on a job by job basis. This would involve a line-by-line detailed check of the actual physical installation against the latest P&I diagrams issue, job specifications, piping hanger and support drawings, vendor drawing, etc., for erection of the unit in accordance with all drawings and applicable specification. The systems would also be checked from an operating viewpoint for proper location and orientation of valves, vents, drains, steam tracing and traps, sample connections, etc. Punch lists of deviations,Installation errors, missing items, etc., shall be prepared and given to the appropriate construction department for correction or completion. Also included in this inspection and check-out would be:• Vessel Internals - This would include going through each tower and vessel to check the installation of trays, baffles, demisters, spargers, etc., and verifying that the dimensions of all weirs, downcomers, distributors, thermowells, etc., are within specification and are properly oriented, as well assuring the internal cleanliness of each vessel prior to final closure.• Non-operating Adjustments - All non-operating adjustments, packing of pumps and valves and cold alignment of equipment performed by the construction subcontractors should be spot checked, witnessed or periodically inspected to ensure proper records are being kept and recorded for turnover.• Piping - Check lists would be prepared on each hydrostatic test system before the system is released for hydrostatic testing. Completion of this punch lists by the construction contractor would be required before the test system is released for testing. Post-hydro punch lists would be prepared and followed through on to ensure that the systems were fully completed and ready for pre-commissioning.• Electrical Installation - Each electrical circuit and motor installation and their electrical polarity check and insulation resistance measurement would be demonstrated by electrical subcontractor to the Commissioning Subcontractor Team.• Instrument Installation - Review of instrument installation of correctness according to the instrument drawings and specification. The Commissioning Subcontractor Team would witness and/or approve all instrument calibration and check out procedures or work performed by instrument subcontractor.• System Pressure Testing - Although the construction contractor is responsible for the actual pressure testing of each system prior to mechanical completion, the Commissioning Subcontractor Team would review the test program and the methods used to ensure satisfactory tightens.3.2 Pre-Commissioning PeriodThe site phase of the project will commence at approximately 60% construction completion and activities will be mainly centred on:• Progression of all of the procedures developed during the Home office phase of the project• Co-ordinating system turnover and completion• Monitoring and reporting progress• Co-ordinating resources, including sub-contract and vendor support• Liaising with licensorsMain activities developed during Pre-Commissioning phase are:Punch-ListingPunch-Listing will be undertaken on a systems basis. An integrated team will be formed to participate in Punch-Listing. An initial Punch-List will be undertaken immediately prior to system handover for Pre-Commissioning purpose. This will probably occur at around the hydro test time. Punch-List items generated at this stage will be incorporated into the Project master Punch-List system. A final Punch-List will be undertaken by system immediately prior to the commencement of commissioning activities. This will be a less stringentPunch-List and aimed at checking the system over before introducing hydrocarbonsUtilisation of the Pre-Commissioning check sheets will assist in completing a full range of required checks. Punch-Listing progress will be recorded on an A3 set of P&IDs.System CleaningThis would include directing the cleaning of systems either by flushing, blowing or chemical cleaning by issuing directives for the necessary temporary connections, utilities and proper line up of the system to be cleaned. When the services of a chemical cleaning subcontractor are required, the Commissioning Team will monitor his performance to ensure a satisfactory cleaning job. Before each system is closed for operating, the lines and equipment would be inspected for cleanliness. Cleaning progress will be recorded on an A3 set of P&IDs.Equipment Run-InThis would include planning and co-ordinating Vendor representatives for the running in of the equipment and obtaining the necessary utilities to accomplish the run-in for equipment such as blowers, pumps, compressor, motors, turbines, and other machinery or mechanical equipment without process fluids before start-up.Vessel Loading
This phase would ensure that all catalysts, packing, resins and desiccant loading is performed in a proper manner and accurate records and samples of each material loaded are retained. When all the activities foreseen in the Pre-Commissioning phase (the Process
Units will be ready to receive hydrocarbons, most of the utility systems will be live to the respective units and all of the hydrocarbon lines will be positively isolated at the unit battery limits) have been performed successfully a Ready for Commissioning Certificate will be issued and so Commissioning activities can start.
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 2:[สำเนา]
คัดลอก!
3.
Pre-ว่าจ้างกิจกรรมPre-ว่าจ้างเริ่มต้นเมื่อพืชหรือระบบประสบความสำเร็จเสร็จสิ้นวิศวกรรม ที่พบบ่อย แต่กิจกรรม Pre-ว่าจ้างทับซ้อนวิศวกรรมกิจกรรมเสร็จสิ้นและด้วยเหตุนี้พืชควรจะแยกออกเป็นแพคเกจระบบการจัดการได้อย่างง่ายดาย, แพคเกจแต่ละระบบจะ Pre-หน้าที่โดยรวมและ isolations ที่ขอบเขตของแพคเกจระบบจะได้รับการรักษาจน เสร็จสิ้นกิจกรรมก่อนการว่าจ้าง กิจกรรมการว่าจ้างก่อนรวมถึงการตรวจสอบตามมาตรฐานการออกแบบการตรวจสอบสถานะของการไฟฟ้าเครื่องกลและการติดตั้งเครื่องมือที่ใช้ในอุปกรณ์ล้างและทำความสะอาดกิจกรรมการอบแห้งเป็นต้น
3.1
วิศวกรรมตรวจสอบแล้วเสร็จและส่งมอบระหว่างกาลทันทีก่อนที่จะมีการทดสอบน้ำของแต่ละระบบเป็นหมัดรายชื่อจะได้รับการดำเนินการโดยทีมงานแบบบูรณาการราย Punch- ประกอบด้วยการก่อสร้างและ EPC
ว่าจ้างวิศวกร(จากสาขาวิชาที่เกี่ยวข้อง) เมื่อทุกคน "เป็น" รายการประเภทได้รับการล้างและมีจำนวนน้อย แต่จัดการของ "B" รายการประเภทที่เหลือเป็นส่งมอบสามารถก้าวหน้าจากการก่อสร้างไปยังกลุ่มการว่าจ้างที่ ตั้งแต่เสร็จสิ้นกลได้รับความสำเร็จกับรายการยกเว้นที่ตกลงกันไว้ก็จะถูกจัดเป็นส่งมอบระหว่างกาลที่จะอนุญาตให้ก่อสร้างแล้วเสร็จและกิจกรรม Pre-ว่าจ้างพร้อมกัน การควบคุมและความรับผิดชอบในการทำงานในส่วนที่เหลือระบบที่มีการว่าจ้างกลุ่ม การก่อสร้างใด ๆ ที่จะต้องได้รับอนุญาตเป็นลายลักษณ์อักษรจากวิศวกรตะกั่วว่าจ้างหน่วยกระบวนการโดยเฉพาะอย่างยิ่ง อนุญาตในการทำงานโดยแต่ละงาน นี้จะเกี่ยวข้องกับบรรทัดโดยบรรทัดตรวจสอบรายละเอียดของการติดตั้งทางกายภาพที่เกิดขึ้นจริงกับล่าสุดพีแอนด์ไอปัญหาแผนภาพรายละเอียดงานที่แขวนท่อและภาพวาดสนับสนุนการวาดภาพของผู้ขาย ฯลฯ สำหรับการก่อสร้างของหน่วยงานให้สอดคล้องกับภาพวาดและบังคับ สเปค ระบบจะมีการตรวจสอบจากมุมมองการดำเนินงานสำหรับตำแหน่งที่เหมาะสมและการวางแนวของวาล์ว, ช่องระบายอากาศ, ท่อระบายน้ำ, การติดตามการอบไอน้ำและดักการเชื่อมต่อตัวอย่าง ฯลฯ รายการหมัดของส่วนเบี่ยงเบน,
ข้อผิดพลาดการติดตั้งรายการที่หายไป ฯลฯ จะต้องจัดทำและ ให้กับฝ่ายการก่อสร้างที่เหมาะสมสำหรับการแก้ไขหรือเสร็จสิ้น ก็รวมอยู่ในการตรวจสอบและเช็คเอาท์จะเป็น:
•เรือ Internals - นี้จะรวมถึงจะผ่านแต่ละอาคารและเรือเพื่อตรวจสอบการติดตั้งถาด, แผ่นกั้น, demisters, กระจายก๊าซ ฯลฯ และตรวจสอบว่าขนาดของทำนบทั้งหมด downcomers, ผู้จัดจำหน่าย, thermowells ฯลฯ อยู่ในสเปคและจะเน้นอย่างถูกต้องเช่นเดียวกับความเชื่อมั่นกับความสะอาดภายในของเรือแต่ละก่อนที่จะมีการปิดสุดท้าย.
•การปรับการดำเนินงานที่ไม่เป็น - สิ่งที่ปรับเปลี่ยนการดำเนินงานที่ไม่ได้บรรจุของปั๊มและวาล์วและเย็น การจัดตำแหน่งของอุปกรณ์ดำเนินการโดยผู้รับเหมาช่วงการก่อสร้างควรจะตรวจสอบจุดที่เห็นหรือตรวจสอบเป็นระยะ ๆ เพื่อให้แน่ใจว่าการบันทึกที่เหมาะสมจะถูกเก็บไว้และบันทึกไว้สำหรับผลประกอบการ.
•ท่อ - ตรวจสอบรายการที่จะได้รับการจัดทำระบบการทดสอบ hydrostatic แต่ละก่อนที่ระบบจะถูกปล่อยออกมาสำหรับการทดสอบไฮโดรลิก . ความสำเร็จของรายการหมัดนี้โดยผู้รับเหมาการก่อสร้างจะต้องทดสอบระบบก่อนที่จะถูกปล่อยออกมาสำหรับการทดสอบ รายการเจาะโพสต์น้ำจะได้รับการเตรียมความพร้อมและปฏิบัติตามผ่านเพื่อให้แน่ใจว่าระบบได้เสร็จสมบูรณ์และพร้อมสำหรับการก่อนการว่าจ้าง.
•การติดตั้งไฟฟ้า - แต่ละวงจรไฟฟ้าและการติดตั้งมอเตอร์และขั้วไฟฟ้าของพวกเขาตรวจสอบและการวัดความต้านทานของฉนวนจะต้องแสดงให้เห็นถึง ผู้รับเหมาช่วงไฟฟ้ากับการว่าจ้างผู้รับเหมาช่วงทีม.
•การติดตั้งเครื่องมือ - ตรวจสอบการติดตั้งเครื่องมือของความถูกต้องตามรูปวาดเครื่องมือและข้อกำหนด ว่าจ้างทีมงานผู้รับเหมาช่วงจะเป็นพยานและ / หรืออนุมัติการสอบเทียบเครื่องมือทั้งหมดและตรวจสอบขั้นตอนการทำงานหรือดำเนินการโดยผู้รับเหมาช่วงเครื่องดนตรี.
•การทดสอบความดันระบบ - แม้ว่าเหมาก่อสร้างเป็นผู้รับผิดชอบสำหรับการทดสอบความดันที่เกิดขึ้นจริงของแต่ละระบบก่อนที่จะเสร็จสิ้นกลการว่าจ้าง ทีมงานผู้รับเหมาช่วงจะทบทวนการทดสอบโปรแกรมและวิธีการใช้เพื่อให้แน่ใจกระชับที่น่าพอใจ.
3.2
ระยะเวลาก่อนการว่าจ้างระยะที่เว็บไซต์ของโครงการจะเริ่มที่ประมาณ60% เสร็จสิ้นการก่อสร้างและกิจกรรมที่จะเป็นศูนย์กลางหลักในการ:
•ความคืบหน้าของทุกขั้นตอน
การพัฒนาในช่วงระยะโฮมออฟฟิศของโครงการ•ผลประกอบการระบบการประสานงานและความสมบูรณ์•การตรวจสอบและความคืบหน้าการรายงาน•ทรัพยากรประสานรวมทั้งย่อยสัญญาและการสนับสนุนผู้ผลิต•ประสานงานกับผู้ออกใบอนุญาตกิจกรรมหลักการพัฒนาในช่วงPre-ว่าจ้างคือหมัด-Listing Punch-รายจะดำเนินการบนพื้นฐานของระบบ ทีมงานแบบบูรณาการจะเกิดขึ้นในการเข้าร่วม Punch-รายชื่อ เริ่มต้นรายชื่อหมัดจะดำเนินการทันทีก่อนที่จะส่งมอบระบบเพื่อวัตถุประสงค์ Pre-ว่าจ้าง นี้อาจจะเกิดขึ้นในช่วงเวลาการทดสอบน้ำ รายการ Punch รายชื่อที่สร้างในขั้นตอนนี้จะรวมอยู่ในโครงการต้นแบบระบบ Punch รายชื่อ สุดท้ายหมัดรายชื่อจะได้รับการดำเนินการโดยระบบทันทีก่อนที่จะเริ่มกิจกรรมการว่าจ้าง นี้จะเป็นเข้มงวดน้อยกว่ารายชื่อหมัดและมุ่งเป้าไปที่การตรวจสอบระบบในช่วงก่อนที่จะแนะนำไฮโดรคาร์บอนใช้ประโยชน์ของแผ่นตรวจสอบก่อนการว่าจ้างจะให้ความช่วยเหลือในการกรอกแบบครบวงจรของการตรวจสอบที่จำเป็น ความคืบหน้า Punch-รายการจะได้รับการบันทึกไว้ในชุด A3 P & รหัส. ทำความสะอาดระบบนี้จะรวมถึงผู้กำกับการทำความสะอาดของระบบทั้งโดยการล้างเป่าหรือสารเคมีทำความสะอาดโดยการออกคำสั่งสำหรับการเชื่อมต่อชั่วคราวที่จำเป็นสาธารณูปโภคและเส้นที่เหมาะสมของระบบเพื่อจะทำความสะอาด เมื่อใช้บริการของการทำความสะอาดสารเคมีผู้รับเหมาช่วงจะต้องว่าจ้างทีมงานจะตรวจสอบการทำงานของเขาเพื่อให้แน่ใจว่างานทำความสะอาดที่น่าพอใจ ก่อนที่แต่ละระบบจะปิดการดำเนินงานสายและอุปกรณ์จะได้รับการตรวจสอบความสะอาด ความคืบหน้าของการทำความสะอาดจะได้รับการบันทึกไว้ในชุด A3 P & รหัส. อุปกรณ์ทำงานในนี้จะรวมถึงการวางแผนและตัวแทนผู้ขายประสานการทำงานในส่วนของอุปกรณ์และได้รับสาธารณูปโภคที่จำเป็นเพื่อให้บรรลุการทำงานในสำหรับอุปกรณ์เช่นเครื่องเป่า, ปั๊ม, คอมเพรสเซอร์, มอเตอร์, กังหันและเครื่องจักรอื่น ๆ หรืออุปกรณ์เครื่องจักรกลโดยไม่ต้องของเหลวในกระบวนการก่อนที่จะเริ่มต้นขึ้น. เรือกำลังโหลดช่วงนี้จะให้แน่ใจว่าตัวเร่งปฏิกิริยาทั้งหมดบรรจุเรซินและโหลดสารดูดความชื้นที่จะดำเนินการในลักษณะที่เหมาะสมและมีการบันทึกที่ถูกต้องและตัวอย่างวัสดุแต่ละโหลดจะถูกเก็บไว้ เมื่อกิจกรรมทั้งหมดที่มองเห็นในระยะก่อนการว่าจ้าง (กระบวนการหน่วยจะพร้อมที่จะได้รับสารไฮโดรคาร์บอนส่วนใหญ่ของระบบสาธารณูปโภคที่จะมีการถ่ายทอดสดไปยังหน่วยงานที่เกี่ยวข้องและทุกสายไฮโดรคาร์บอนจะแยกทางบวกที่ขีดจำกัด ของแบตเตอรี่เครื่อง) ได้รับการดำเนินการประสบความสำเร็จพร้อมสำหรับการรับรองการว่าจ้างจะมีการออกและอื่น ๆ กิจกรรมการว่าจ้างสามารถเริ่มต้น















การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 3:[สำเนา]
คัดลอก!
3 . ก่อนการว่าจ้าง
ก่อนว่าจ้างกิจกรรมเริ่มเมื่อพืช หรือใช้ระบบเครื่องกล , เสร็จ บ่อย อย่างไรก็ตาม ก่อนการว่าจ้างกิจกรรมซ้อนกิจกรรมจบเครื่องกลและสำหรับเหตุผลนี้พืชที่ควรจะแยกออกเป็นแพคเกจของระบบที่จัดการง่ายแต่ละระบบจะได้รับแพ็คเกจก่อนรับหน้าที่เป็นทั้งและ isolations ที่ขอบเขตของระบบจะถูกเก็บรักษาไว้จนกว่าจะเสร็จก่อนการจัดกิจกรรม ก่อนการว่าจ้างกิจกรรมต่างๆรวมถึง : การตรวจสอบการออกแบบที่สอดคล้องกัน การตรวจสอบสถานะของไฟฟ้า ติดตั้งเครื่องจักรกล และอุปกรณ์ ใช้ในอุปกรณ์ล้างและทำความสะอาด กิจกรรมการอบแห้งฯลฯ
3.1 กลเสร็จตรวจสอบ&ระหว่างแฮนด์
ทันทีก่อนที่จะทดสอบพลังของแต่ละระบบ รายการเจาะจะดำเนินการโดยบูรณาการ Punch - รายชื่อทีม ประกอบด้วย การก่อสร้างและการว่าจ้างวิศวกร ( EPC
จากสาขาวิชาที่เกี่ยวข้อง ) เมื่อทั้งหมด " " รายการประเภทได้รับการล้าง และเป็นจำนวนเงินที่เล็ก ๆแต่ง่ายต่อการจัดการของ " บี " รายการประเภทอยู่ด้านซ้ายเป็นระบบที่สามารถสร้างขึ้นจากการว่าจ้างของกลุ่ม ตั้งแต่จบเครื่องกลได้รับความกับตกลงรายการข้อยกเว้น มันเป็น classed เป็นระบบชั่วคราวให้เสร็จก่อนการว่าจ้างก่อสร้างและกิจกรรมพร้อมกัน ควบคุมและรับผิดชอบงานในส่วนระบบ มีการว่าจ้างกลุ่มงานก่อสร้างใด ๆ จะต้องได้รับอนุญาตเป็นลายลักษณ์อักษรจากตะกั่วการว่าจ้างวิศวกรของหน่วยกระบวนการที่เฉพาะเจาะจง ได้รับอนุญาตจะได้รับในงาน โดยงานพื้นฐาน บรรทัดนี้จะเกี่ยวข้องกับการตรวจสอบรายละเอียดของการติดตั้งทางกายภาพที่แท้จริงกับล่าสุด P &ผมภาพปัญหา ประเภทงานท่อ , ไม้แขวนรูปวาดและภาพวาด , สนับสนุน , ผู้ขาย ฯลฯสำหรับการก่อสร้างของหน่วยตามแบบและข้อกำหนดที่เกี่ยวข้อง ระบบจะถูกตรวจสอบจากมุมมองสำหรับตำแหน่งที่เหมาะสม และการดำเนินงานของวาล์วระบาย ระบายไอน้ำ , ติดตามและกับดักตัวอย่างการเชื่อมต่อ ฯลฯ ชกรายการเบี่ยงเบน
ติดตั้งข้อผิดพลาด รายการที่ขาดหายไป เป็นต้นจะได้เตรียมให้หน่วยงานก่อสร้างที่เหมาะสมเพื่อแก้ไข หรือ ความสมบูรณ์ นอกจากนี้ในการตรวจสอบนี้และแบบด่วนจะ :
- เรือ internals - นี้จะรวมไปถึงแต่ละหอ และเรือ เพื่อตรวจสอบการติดตั้งแผ่นกั้น demisters spargers , ถาด , ฯลฯ และการตรวจสอบว่าขนาดของฝาย , downcomers ผู้จัดจำหน่าย thermowells ฯลฯ
การแปล กรุณารอสักครู่..
 
ภาษาอื่น ๆ
การสนับสนุนเครื่องมือแปลภาษา: กรีก, กันนาดา, กาลิเชียน, คลิงออน, คอร์สิกา, คาซัค, คาตาลัน, คินยารวันดา, คีร์กิซ, คุชราต, จอร์เจีย, จีน, จีนดั้งเดิม, ชวา, ชิเชวา, ซามัว, ซีบัวโน, ซุนดา, ซูลู, ญี่ปุ่น, ดัตช์, ตรวจหาภาษา, ตุรกี, ทมิฬ, ทาจิก, ทาทาร์, นอร์เวย์, บอสเนีย, บัลแกเรีย, บาสก์, ปัญจาป, ฝรั่งเศส, พาชตู, ฟริเชียน, ฟินแลนด์, ฟิลิปปินส์, ภาษาอินโดนีเซี, มองโกเลีย, มัลทีส, มาซีโดเนีย, มาราฐี, มาลากาซี, มาลายาลัม, มาเลย์, ม้ง, ยิดดิช, ยูเครน, รัสเซีย, ละติน, ลักเซมเบิร์ก, ลัตเวีย, ลาว, ลิทัวเนีย, สวาฮิลี, สวีเดน, สิงหล, สินธี, สเปน, สโลวัก, สโลวีเนีย, อังกฤษ, อัมฮาริก, อาร์เซอร์ไบจัน, อาร์เมเนีย, อาหรับ, อิกโบ, อิตาลี, อุยกูร์, อุสเบกิสถาน, อูรดู, ฮังการี, ฮัวซา, ฮาวาย, ฮินดี, ฮีบรู, เกลิกสกอต, เกาหลี, เขมร, เคิร์ด, เช็ก, เซอร์เบียน, เซโซโท, เดนมาร์ก, เตลูกู, เติร์กเมน, เนปาล, เบงกอล, เบลารุส, เปอร์เซีย, เมารี, เมียนมา (พม่า), เยอรมัน, เวลส์, เวียดนาม, เอสเปอแรนโต, เอสโทเนีย, เฮติครีโอล, แอฟริกา, แอลเบเนีย, โคซา, โครเอเชีย, โชนา, โซมาลี, โปรตุเกส, โปแลนด์, โยรูบา, โรมาเนีย, โอเดีย (โอริยา), ไทย, ไอซ์แลนด์, ไอร์แลนด์, การแปลภาษา.

Copyright ©2024 I Love Translation. All reserved.

E-mail: