JRR will be taking care of the customs clearance on both Thai and Malaysia side as they are doing the documents and will be using their agent.
Please clarify regarding crane as at site the shipment will be offloaded by client.
Also please confirm why a low bed trailer is required when the height is only 3.2m, wouldn't a normal Trailer be sufficient?