Please help to continued HOLD stop all ENGINEERING / PROCUREMENT PRE-ORDER work activity of LLTE Project for this week, We have intention to force OWNER to approve process of CHANGE REQUEST that submit before continue remaining work.
Note I will update information again on Wed 3-Feb-16 ( Thai Oil will bring to the committee on this Tuesday)
For Procurement POST ORDER Expediting 10 packages can be start work. (Thai Oil to issued Work Order Under TermService already) and I will setup crated NEW Project Number within this week