Despite Lassiter’s interest and urging, implementing the new system took much longer than was planned. Delays in issuing the purchase order and testing the software only added to the time to make the system operational. Training finally took place in August 2006. The training went well, but data migration became a serious problem. On the final day of training, Lassiter told Kovecki to migrate the data in the current workstation systems to the new system. Kovecki had considerable problems doing so as less than 15 percent of the data rolled over into the proper assignments. Because there was no documentation on the old software to refer to, it took him until late 2006