elow are my comments on your progress:
1. Progress shall be considered for: Material received and Installation. Mean Progress will be approved only if material or service received on site or installation has been done. Any PO issued by CNS to vendor / supplier should not be considered as progress.
2. In your progress, you show you have completed 100% for civil work ? I don’t think that’s correct. Ramp for the building, concrete column, and waste water tank still have not been completed. Inside this include steel structure which is still not completed.
3. You will need to re check also for structural completion