Dear All,
Please be informed that rig E-08 equipment shall be arrived to Laem Chabang port on 19th July .The moving plan as below :
July 18th : Sent 3 trailers from our yard to Laem Chabang port
July 19th---20th:Transfer E08 equipment to pointed area for customs clearance .
July 21st---23rd :TransferE08 equipment from LCB port to our yard .
Pum:
Please ask more information as below:
1.Please confirm the vessel and ship owner;
2. Which port will be berth for the vessel;
3.Please confirm where we can store our equipment
4.Pls confirm any fee for store up cargo;
5.Please rent two 50 tons crane for moving E08 rig equipment on 19th & 20th ; Rent one 50ton crane for loading the first convoy on 21st July and the second trip on 22nd July ;Rent two 50tons cranes for loading heavy equipment on last day 23rd July
Pup & Gems:
Please arrange trailers as :21st 11 trailers ;22nd 11 trailers ;23rd :11trialers .
All of heavy equipment will be move on 23rd July ,please contact police in advance .
Please make sure all the driver understand our HSE policy, make sure trailers in good condition, make sure they know the rest point, make plan to let mechanic follow up heavy trailer, make good manage for fill up diesel,and so on as per long distance moving requirement;
Pls have meeting with all the trailers transport during Father day.
Beer :
Pls arrange 4 GWT11 employees go to Laem Chabang port on 18th July for loading and offload during E08 moving .inform them preare full PPE and Reflect vest jacket & tag lines ,warning tape .
Any suggestion please feel free to discuss .