With regarding to the below, there are some matter that we have just been informed from the forwarder as well :
1 : 2 x 40 ft HQ schedule (load 15/3) earlier that we advise you ETD 18 / ETA 22 but there are the matter of delay incoming of the vessel at pier so finally they just advise the new schedule as per the mail that Aunyarin sent you yesterday. (From you Old P/O). So, the new ETD is 20/3 ETA 25/3
2. We plan together on another schedule of 2 x 40 ft HQ (New P/O) but due to the production and vessel plan , finally we have to arrange the to split the shipment to be ….
1 x 20 ft to load today 18/3 and ETD 20/3 and ETA 25/3
1 x 40 ft to load 22/3 and ETD 25/3 ETA 29/3