Today, we had 2 main activities happen.
1. Air Condition arrival and start installation expect to complete by Thursday. We wait the stand from STEC and clear space outside Datacenter so we can finish Compressor installation.
2. Re-visit the Diesel Tank issues, The additional 2 attempts were because we couldn’t find the root cause of the problem since the leakage is so tiny that the installation team could not see the real spot and had to wait to see the accumulated fuel drop to finally locate it. Now they confidence the root cause is outside the bolt. They plan to fix it by cold welding method by Wednesday 23-Dec. By causing delay and provide confidence in this method. Generator company will provide extended warranty on Diesel Fuel Tank leaking again from this spot.
We also had 1 reschedule for Access Control System to Thursday. As the Wednesday will be busy from many project activities. This reschedule will not impact overall project completion as it take only 1day and no dependency to other project activities.