The method statements for road construction have been approved.
The method statement for cable ductbank was submitted and Powerchaina have given comments and GKE will revise and resubmit by 22st July.
The CPAC concrete mix design with corrosion protective admixture and relevant support documents, will be submitted by 22nd July, for Powerchina to review and provide relevant review comments respectively.