Thanks for the BOQ.
We had a quick review at it.
Some items are in this BOQ but missing in dwg (ex: ATS...)
Some qty and cable size are not as per expected/actual.
Our team will therefore put back the unit rate on GES BOQ.
Any amendment under item G that we have knowledge (qty, scope, item…) will be done in red.
Item G will be ready by Monday 20th June.
For the remaining Item B, D & E, we will follow GES qty as we won’t have time to survey in detail.
Therefore any discrepancy will be subject to +/- VO.
We would not be in measure to talk in that case of a lump sum project.
Note that due to current work load, item B, D & E pricing will be ready for next Friday 24th June only