Installation instructions
First, disengage the motor clutch and switch the controller on by SW1. Push the gate to mid way position. For N.O. limit switch type, both LED L3 & L6 are off: for N.C. type, L3 & L6 are lit. Then push the gate manually to the open limit position. If N.O. limit switch is used, LED L3 is lit: for N.C. type, it is off. Push the gate to the close limit position. If N.O. limit switch is used, LED L6 is lit: for N.C. type, it is off. Now push the gate to the mid position. Switch SW1 to off for at least 5 seconds and then switch on. Engage the motor’s clutch. In the mean time, do not test any limit switches. The gate should open when first triggered, otherwise quickly switch SW1 off. Exchange the wires connection between terminal 15 & 16 if it closes when tested in this manner. The direction of gate’s movement must follow the signal given by the control panel. The L1 lit green indicates gate opening and L5 lit red indicates gate closing.