Most importantly we must undertake glue adhesion trials on 6600005 to glass. A change in manufacturer can have significant effect on this- packing pressure and resultant surface tension can have an effect on the ability to adhere and not just the material grade. ORA need to process these part with the primers as per SOPs and glue them to glass and send parts to ARB to me for load testing under cold and heat.
This process will take one month from receipt of OTS to ORA to complete before production approval can be given.
For 6604027 parts need to be assembled at ORA into frames and review undertaken of product compared with supply now to new level supply. For receipt of OTS this will take 5 days to approve via ORA and CC ARB in results..