From purchase history records in FY16 (23 Apr 15 to 13 May 16), our maintenance team have already sent tooling & Jig to our contactor for hardening steel about 28 times or $2K per year. We have an opportunity to cancel sending tooling & Jig to our contactor for hardening steel by purchase electric hardening furnace. This equipment consists of high efficiencies electric furnace and low energy consumption. We can reduce delivery lead time from our contactor to Gammatron. Therefore, we can support production requirement to meet delivery output and schedule per demand planning and requirement.