13. A chief audit executive may use risk analysis in preparing work schedules. Which of the following is not considered in performing a risk analysis?
A. Issues relating to organizational governance.
B. Skill available on the internal audit staff.
C. Result of prior engagement.
D. Major operating changes..
Answer (B) is correct.
REQUIRED:
DISCUSSION: